  1. PT. BSM, is a company that operates in the manufacturing sector by producing Mechanical Seals and is also a distributor of the Nippon Pillar Japan brand. Production planning and control is necessary to ensure that all processes function smoothly and production efficiency and effectiveness are achieved. PT.BSM's production system implements Make To Order (MTO), in which production activities are carried out when the customer places an order. This process will take place from raw materials, and semi-finished goods to finished products. This will pose a risk to the production process if the raw materials to be produced are not yet available. So it is necessary to have an analysis of planning and inventory control to expedite the production process. Therefore, the purpose of this study is to plan and control raw materials in accordance with requests from customers in the future using the Material Requirement Planning (MRP) method with the Lot For Lot (LFL) technique, after calculating the MRP with The Lot For Lot (LFL) technique obtained the planning results for mechanical seal raw material requirements for 2023 every month. Based on MRP calculations using the Lot For Lot technique, mechanical seal raw materials can be planned and controlled for the next 12 periods.

           Key Words: LFL, Mechanical Seals, MRP,  Supplies

References

Anugrah, M., & Setiawannie, Y. (2021). Analisa Pengendalian Persediaan Bahan Baku TBS Minyak Sawit Dengan Metode MRP. IESM Journal (Industrial Engineering System and Management Journal), 2(1), 67-73.

Ardika, D. A. P., Maria, E., & Isbandi, T. (2022). PERENCANAAN PERSEDIAAN BAHAN BAKU DENGAN METODE MRP (MATERIAL REQUIREMENT PLANNING) MENGGUNAKAN PENDEKATAN TEKNIK LOTSIZING.

Arief, J., Hakim, R., & Surabaya, N. (2022). ANALISA SISTEM MANAJEMEN MATERIAL INSULATION PLAN PADA PROYEK KCR 60M KE-5 DIVISI KAPAL PERANG PT PAL INDONESIA Jurusan Teknik Perkapalan , Institut Teknologi Adhi Tama Surabaya Jurusan Teknik Perkapalan , Institut Teknologi Adhi Tama Surabaya Sistem pere. 1–9.

Dadang Kurnia, S. B. B. N. I. (2018). Pengendalian Bahan Baku pada produk tas dengan metode MRP untuk meminimalkan biaya penyimpanan (6 bulan). Jitmi, 1, 22–28.

Damayoki, I. M. (2022). Analisis Perencanaan Persediaan Bahan Baku dengan Metode Material Requirement Planning (MRP) di UD. Karya Logam Steel (Raw Material Inventory Planning Analysis with Material Requirement Planning (MRP) Method at UD. Karya Logam Steel) (Doctoral dissertation, Universitas 17 Agustus 1945 Surabaya).

Prita Hindarto, R., & Dalulia, P. (2021). PERENCANAAN KEBUTUHAN MATERIAL UNTUK PRODUK DISPOSABLE PROTECTIVE MASK SELAMA PANDEMI COVID 19 DI KOTA MALANG Diterima : Journal of Industrial View, 03, 35–42.

Purnama, D. H. D., & Pulansari, F. (2020). Perencanaan Dan Pengendalian Bahan Baku Produksi Kerupuk Dengan Metode Mrp Untuk Meminimumkan Biaya Persediaan Bahan Baku Di Ud. Xyz. Jurnal managemen industri dan teknologi.

Rifa’i, M. R. (2022). ANALISIS PENGENDALIAN PERSEDIAAN BAHAN BAKU DENGAN METODE MATERIAL REQUIREMENT PLANNING (Studi Kasus: PT. Aneka Adhilogam Karya). Jurnal Cakrawala Ilmiah, 1(7), 1757-1768.

Saputra, R. A., Kholidasari, I., Sundari, S., & Setiawati, L. (2021). Analisis Perencanaan Bahan Baku Di Ud. Aa Dengan Menerapkan Metode Material Requirement Planning (Mrp). Jurnal Logistik Indonesia, 5(1), 1-12.

Sari, D. H., & Budiawan, W. (2017). Analisis Penerapan Material Requirement Planning (MRP) dengan Mempertimbangkan Lot Sizing dalam Pengendalian Persediaan Kebutuhan Bahan Baku Xoly untuk Pembuatan Alkyd 9337 pada PT. Pjc. Industrial Engineering Online Journal, 6(1).

Supriyadi, E., & Nurdewanti, R. (2022). Pengendalian Persediaan Bahan Baku dengan Metode Activity Based Costing (ABC) dan Economic Order Quantity (EOQ) di CV. XYZ. Briliant: Jurnal Riset dan Konseptual, 7(1), 211.

Tanisri, R. H. A., & Rye, E. (2022). Pengendalian Persediaan Bahan Baku Roda Caster Menggunakan Metode Mrp (Material Requirement Planning) Di Cv Karya Teknik Makmur. Jurnal Inkofar, 6(1), 52–60.

Tejakusuma, T. Y. (2018). Analisis Material Requirement Planning (MRP) di C-Maxi Alloycast. Integrated Lab Journal, 5(2).

Wahyuni, A., & Syaichu, A. (2015). Perencanaan Persediaan Bahan Baku Dengan Menggunakan Metode Material Requirement Planning (Mrp) Produk Kacang Shanghai Pada Perusahaan Gangsar Ngunut-Tulungagung. Spektrum Industri, 13(2), 141.

Wardhana, J. T., & Suparto, S. (2023, March). Analisis Perencanaan Persediaan Bahan Baku dengan Metode Material Requirement Planning (MRP) di PT. PG Candi Baru Sidoarjo. In Prosiding SENASTITAN: Seminar Nasional Teknologi Industri Berkelanjutan (Vol. 3).

Yuwono, M. R. A., & Saptadi, S. (2022). Analisis Perbandingan Metode EOQ, Metode POQ, dan Metode MIN-MAX dalam Pengendalian Persediaan Komponen Pesawat Terbang Boeing 737NG (Studi Kasus: PT Garuda Maintenance Facility Aeroasia Tbk.). Industrial Engineering Online Journal, 11(3).

Downloads

Published

2024-04-22

How to Cite

Gina Hidayatul Kamila, & Ade Momon. (2024). Analisis Penerapan Metode Material Requirement Planning (MRP) dalam Perencanaan dan Pengendalian Bahan Baku pada PT. BSM. Industrika : Jurnal Ilmiah Teknik Industri, 8(2), 238–246. https://doi.org/10.37090/indstrk.v8i2.1234