Identifikasi dan Usulan Menangani Waste pada Proyek Mesin Selectifier dengan Pendekatan Lean Project Management Di PT. Z

Authors

  • Abdullah Firmansyah Universitas Singaperbangsa Karawang
  • Ade Momon Universitas Singaperbangsa Karawang

DOI:

https://doi.org/10.37090/indstrk.v8i3.1299

Abstract

The delay of a project can occur due to poor planning of its necessary resources, causing waste or waste. The purpose of this research is to find out the waste and its factors that can potentially occur in the selectifier machine project and know the viable solution to choose to deal with the waste. Then careful planning is required by applying the Lean Project Management methodology, where waste and harm can be found using scoring matrices and fishbone diagramming tools. Based on the analysis results in the selectifier machine project at PT. Z, the potential waste appears, namely waste waiting, defects and overprocessing. Waste and its potential causes are materials or components that are late dating, workers waiting for certain information, machines or tools supporting machine manufacturing are damaged, manufacturing process is not suitable for SOP, materials or components of poor quality, less scrupulous workers, poor working techniques. And according to the evaluation matrix, the best solution obtained is to perform other tasks that do not involve doing material work or using components that have not yet arrived on site, and buying back better materials from vendors.

Keywords : Evaluation Matrix, Fishbone Diagram, Lean Project Management, Waste

References

-Apriana Intan Permatasari, A. P. (2022). Evaluasi Metode Lean Project Management Pada Proyek Pelaksanaan Pembangunan Tangki Premium, ADO, dan RFO di Pertamina RU V Balikpapan (Studi Kasus: PT. Barata Indonesia (Persero). JIME (Journal of Industrial and Manufacture Engineering), 9-22.

Dian, A. (2019). Penerapan Metode Lean Project Management dalam Proyek Konstruksi pada Pembangunan Gedung DPRD Kabupaten Ogan Ilir. Jurnal Teknik Sipil dan Lingkungan, 171-179.

Dimas Ghifari Priandoni, I. A. (2023). Perancangan Waste Response Menggunakan Metode Lean Project Management pada Proyek Smart Building Instalasi Infrastruktur ICT Gedung Baru Field Sangatta. e-Proceeding of Engineering, 2984-2990.

Giari Ayunintya Pratiwi, A. E. (2023). Analisis Waste Pada Proses Produksi Sosis Ayam dengan Pendekatan Lean Manufacturing Di PT. BI. Jurnal Industrika, 208-215.

Harliwanti Prisilia, D. A. (2018). Aplikasi Metode Lean Project Management dalam Pelaksanaan Proyek Konstruksi pada Pembangunan Gedung SMU Negeri 1 Giri Kabupaten Banyuwangi. Jurnal Teknik Waktu, 16-29.

Harpito, A. L. (2018). Evaluasi Perencanaan Dan Pengendalian Proyek Pembangunan Air Bersih Dengan Menggunakan Metode Lean Project Management. Jurnal Teknik Industri, 76-82.

Harpito, Anwardi, Lailatul Syifa Tanjung. (2018). Evaluasi Perencanaan dan Pengendalian Proyek Pembangunan Air Bersih dengan Menggunakan Metode Lean Project Management. Jurnal Hasil Penelitian dan Karya Ilmiah Teknik Industri, 38-45.

Hatpito, A. M. (2019). Identifikasi Waste Proyek Konstruksi Jalan dengan Menggunakan Metode Lean Project Management. Jurnal Hasil Penelitian dan Karya Ilmiah dalam Bidang Teknik Industri, 115-125.

Hilmi Aulawi, D. R. (2022). Analisa Pemborosan Pada Pembangunan Tempat Penahan Tanah di Perusahaan CV. Mega Putra Mandiri Menggunakan Metode Lean Project Management. Jurnal Kalibrasi, 11-16.

Junaidi, I. A. (2021). Perancangan Daftar Waste dengan Menggunakan Pendekatan Lean Project Management Untuk Mengetahui Dampak Biaya pada Proyek Shift To The Front (SttF) Periode 1 PT Xyz. e-proceeding of Engineering, 1-12.

Lukluata Nafiah, W. F. (2019). Perencanaan Proyek Konstruksi Pembangunan Gedung Kampus 3 Uin Walisongo Semarang dengan Metode Lean Project Management. Prosiding Konferensi Ilmiah Mahasiswa UNISSULA (KIMU) 2, 244-254

Muhammad Nurfitriansyah, E. M. (2019). Mengaplikasikan Metode Lean Project Management dan Metode Penjadwalan CCPM dalam Tahap Perencanaan Proyek Konstruksi. Jurnal Teknik Sipil, 200-214.

Philip Small. (2020). Lean Project Management. Independently Published.

Surya Perdana, A. R. (2022). Penerapan Lean Project Management pada Proyek Pembangunan Water Treatment System Di PT Karya Nurindo. Faktor Exacta, 192-199.

T G Amran, D. S. (2019). Evaluating Storage Tank Cap 10000L Manufacturere by Using Lean Project Management. IOP Conference Series: Materials Science and Engineering, 1-9.

Terra Vanzant Stern. (2020). Lean and Agile Project Management. New York: Taylor & Francis Group.

Zulhelmi Andika, M. H. (2022). Analisis Faktor-Faktor Penerapan Lean Construction pada Proyek Konstruksi Gedung Di Kota Banda Aceh. Jurnal Arsip Rekayasa Sipil dan Perencanaan, 77-86.

Downloads

Published

2024-07-19